For most of the internet era, software taught business that location hardly mattered. AI has reversed that. A data centre is worth only as much as the speed at which it can get enough electricity, and that varies sharply from one country to the next. The geography AI needs has little in common with the one the internet let companies ignore.

Some places have what it takes. Finland offers fast permitting, a wind-heavy grid with spare capacity and a cool climate. Germany, South Korea and much of Europe’s old data centre core wait years for a connection. The Gulf has capital and speed, with a war on its doorstep.

Google’s decision to spend at least €13 billion in Finland, including a 22-year contract for up to half the output of a nuclear power station, shows what that preference looks like in practice.

What Makes a Place Good for AI

The most rigorous recent answer comes from the Carnegie Endowment for International Peace. In June it modelled the economics of an illustrative 100 MW AI campus in ten countries.

Its conclusion is that time decides. Carnegie calls it the most important factor in data centre competitiveness.

Time here means the wait from project approval to running chips. It depends on permitting, grid connection queues, transmission and how long it takes to get equipment such as transformers.

Speed Beats Cheap Power

Electricity prices and taxes matter, but less than speed. In Carnegie’s modelling, doubling power prices costs less than a one-year delay.

A delay pushes revenue into the future, and future revenue is worth less. A site with ordinary electricity prices and a fast connection can therefore beat one with cheap power and a long queue.

The Wait, Country by Country

Carnegie estimates the median wait for a major operator in each country. The UAE comes in at about 22 months before any war delays, the United States at 24, and most other countries between 24 and 36.

The UK averages about 34 months. Scotland is nearer three years, while much of the rest of the country faces five or more.

South Korea takes about 40 months and Germany about 42. That leaves Germany almost 18 months behind the United States.

The authors stress that these estimates carry high uncertainty. The order matters more than any single number.

Cool Climates Save Money

Cooler climates raise efficiency. Carnegie’s modelling puts the cost of cooling losses in a hot climate at about $60 million against a cool baseline like Finland.

The paper also points to Canadian hydropower, Northern European renewables and Australian solar potential as strengths.

Land and Labour Matter Least

Construction labour, permitting fees and land have a small effect on total cost. Chips and servers make up most of the spending.

That surprises anyone who assumes cheap land decides where AI goes. Land is part of the story, but a small one.

Why Finland Fits

Carnegie says Finland’s fast timelines reflect policy choices, including parallel permitting and a wind-heavy grid with spare capacity. Transmission bottlenecks remain.

Its Nordic neighbours score well too. Denmark, Norway and Sweden also offer low-tax energy, fast-track permitting and grid investment.

Speed decides the ranking. In Carnegie’s default scenario the United States ranks second of the ten countries. If US projects slip by a year, it falls to fifth, behind the UAE, Finland, Canada and India.

What Google Is Building There

Google’s package covers four data centre projects and energy infrastructure. It is expanding its Hamina site and building new facilities at Kajaani, Vaala and Muhos. Its country manager, Antti Järvinen, called it “the largest single investment in Finland’s history.”

The energy deal is as specific as the buildings. Fortum’s Loviisa nuclear plant will supply up to half its output for 22 years, which Fortum says supports running the plant until 2050. The companies have also signed a letter of intent to explore new nuclear capacity.

A 94 MW battery system is planned near Kajaani for late 2027. Google says it plans to add nuclear, wind and battery capacity.

Finland’s government wants the investment. Prime Minister Petteri Orpo welcomed it with “jobs, lots of jobs for Finns across Finland.” Google expects construction to support more than 37,000 jobs and the finished sites about 7,000.

Where AI Struggles to Land

Europe’s established data centre markets are filling up. JLL counts 3.8 GW of live capacity across Frankfurt, London, Amsterdam, Paris and Dublin, more than double the 2019 level. Vacancy is 6.4% overall and 3.1% in Frankfurt, the tightest market.

Developers are responding by moving out. Hyperscale campuses planned for 2026 to 2028 average 175 km from the major hubs, against 46 km for those delivered in 2022 to 2025. Greenfield sites make up 39% of Europe’s future pipeline, against 8% of recent deliveries.

JLL’s head of data centres for EMEA, Assad Noori, says the deciding factor is increasingly where enough power can be secured, rather than where demand sits.

Germany sits at the bottom of Carnegie’s ranking, because of the longest timelines and a congested grid.

China’s West Had Power and No Customers

Beijing’s Eastern Data, Western Compute initiative tried to push computing towards western provinces. The east had the problem the plan was meant to solve, since data centres in Shanghai, Beijing and Shenzhen strain coal-reliant grids.

The logic was sound on paper. Western solar power can cost as little as 0.19 yuan per kWh, against up to 0.43 yuan in some eastern regions. By 2024, 633 hyperscale and large data centres were operating under the initiative, according to analysts writing in The Strategist.

Then the problems showed up. Some western data centres run at 20% to 30% utilisation, against a policy goal of more than 60%. Renewable output reduction rates in the west exceed 30%, meaning power is generated and then wasted.

Demand sits in the east. Real-time users and fast-changing data are concentrated there, so eastern data tends to be processed in the east. Remote western regions lacked fibre-optic cables, and local customers and skilled staff were scarce.

Guizhou, a flagship province for the plan, has not turned a profit on its data centre expansion.

Beijing Responded With Rules and Subsidies

Xi Jinping rebuked local officials at a high-level Party meeting. “Do all provinces in the country have to develop industries in these directions?” he asked.

Beijing now requires at least 60% utilisation and bans new large data centres in cities where existing ones run below 50%. The authors warn that many western facilities risk becoming “stranded assets.”

Power prices have become a policy tool as well. From November 2025, Chinese data centres that use domestic semiconductors can receive electricity subsidies of up to 50%.

The Gulf Is Fast, Rich and Exposed

The UAE leads Carnegie’s baseline timelines, and JLL counts 2.6 GW under construction across the Middle East with a 13.8 GW planning pipeline. JLL expects regional capacity to quadruple by 2030.

War is the risk. Iran struck two AWS data centres in the UAE and damaged one in Bahrain in March, according to Carnegie.

In Carnegie’s modelling, a six-month war delay leaves the UAE about 1.7% behind the United States. A prolonged war drops it to sixth place, about 7.8% behind.

Power is a second question. Gulf countries produced about 800 TWh of electricity in 2023, against about 1,900 TWh in India, and some analysts doubt Gulf grids can supply constant power at the scale required.

Chips and Minerals Have Addresses Too

The processors behind AI are designed by American companies such as Nvidia and made by TSMC in Taiwan. The lithography machines used to print the most advanced of them come from ASML in the Netherlands, the only company that builds them.

China’s chipmaking is far behind. Carnegie estimates its output at 1% to 4% of US AI chip production in 2025.

The IEA gives one critical mineral specific figures: gallium. China accounts for around 99% of global refined gallium supply, and data centre demand for it could reach more than 10% of today’s total supply by 2030.

Who Ends Up With the Compute

The United States hosted about three-quarters of the world’s advanced AI computing clusters as of May 2025, according to Carnegie. China had about 14% and the EU less than 5%. Australia, Italy and South Korea have no major publicly known AI chip concentrations.

Electricity tells a similar story. The IEA says the United States took 45% of data centre electricity in 2024, China 25% and Europe 15%. That adds up to 85%, and every other country shares the remaining 15%.

Carnegie argues that countries with large amounts of compute on their soil will be better off. Those that offer faster permitting, abundant land, clean power, sovereign capital and technical capacity will have the most leverage.

What It Means for Business

Any company planning its AI strategy now has a geography AI question to answer alongside the software one. Buying capacity means buying a place, with its own wait for power, its own climate and its own political risk.

The useful questions are plain. Where does the capacity sit, who supplies the electricity, how long is the wait for more, and what happens to the business if that region goes dark?

The money is moving fast. JLL expects the four biggest hyperscale providers to spend $725 billion on capital expenditure in 2026, up 77% from $410 billion a year earlier, and AI workloads to make up around half of global data centre capacity by 2030.

The Map Is Not Fixed

Carnegie calls permitting delays, grid backlogs and transmission bottlenecks “the result of policy choices that can be revised.” A country can climb the ranking by speeding up. A one-year speedup would move India to second.

Technology can change the map too. Bloom Energy expects 38% of data centres to be at least partly powered onsite by 2030, which loosens the grid’s hold on location.

The IEA’s range for 2035 shows how unsettled demand is. It runs from about 700 TWh to 1,700 TWh, and its High Efficiency case sits 20% below the base case.

Google has committed to one location in Finland for 22 years, in an industry that spent the last two decades treating location as an afterthought.

Sources

Carnegie Endowment

Helsinki Times

JLL

IEA

The Strategist